Project execution on the
dry dock repairs at the
Port of Durban is 100%
complete, according to a
Transnet Port Terminals
(TPT) spokesperson, who
said the team was currently
compiling the project
close-out report.
Meanwhile, the tender
for the completion of
the detailed design and
feasibility phase of the
adjacent pumphouse
upgrade has been
advertised and will soon be
awarded.