Lüderitz Bay helps switch on wind power

All the project cargo

for Namibia’s first

commercial wind

farm, which is nearing

completion outside Lüderitz Bay,

was successfully handled by the port

itself.

The first consignment of the

Innosun wind turbine project

arrived in the Port of Lüderitz

on the Beautriumph on January

24, according to Taná Pesat,

Namport manager of corporate

communications.

The cargo operations started the

next morning, with the vessel being

unloaded by noon on the following

day.

During the 12-hour operation

700 tons of equipment was

offloaded. This consisted of four

nacelles (the cover housing of the

wind turbine), nine blades and four

generators weighing 70 tons each.

Namport equipment included a

64-ton mobile harbour crane, two

reach stackers, one 25-ton forklift

and a seven-ton forklift.

The second vessel carrying the

remainder of the cargo for the

project was the Constellation, which

berthed in Lüderitz on May 23.

The 80-metre-high towers,

45-metre (9-ton) blades and 90-ton

turbines were offloaded using

tandem lifting to ensure safety,

according to Pesat.

The wind farm is positioned on

the mountains outside Lüderitz and

has changed the skyline and face

of Lüderitz, according to InnoSun

project manager Jan-Barend

Scheepers.

InnoSun is a Namibian-registered

company owned by Namibian and

French shareholders. Ombepo Wind

Park – the new wind farm – is also

partly owned by the Lüderitz Town

Council with a 5% stake.

The turbines will be able to meet

the current power needs of Lüderitz

Bay.

The completion of the project and

assembling the towers on site will

take place within the next 30 days,

according to Scheepers.

InnoSun has further projects

scheduled for another wind farm at

Elizabeth Bay Mine south of Lüderitz

Bay for Namdeb later this year.

“InnoSun looks forward to opening

a bigger wind farm in the Lüderitz

area as the environmental impact

study is being finalised and will be

opened towards the end of 2017,” he

says.

The 80-metre-high towers, 45-metre (9-ton) blades and 90-ton turbines were

offloaded using tandem lifting to ensure safety.